Work In Progress...
Fincon - Finish upright's on south canopy, install fascia plate, anchor plates on wall, grind, weld, prime & clean up
Weather - Cloudy, Rain & Snow Low 30's
Work in progress...
Fincon - Install fascia trim on north canopy's, sand primer, prep for paint, work on south canopy upright's, cut, weld, grind, clean up.
Weather - Partly Cloudy Upper 40's
Work In Progress...
Fincon - Work on south canopy frame, finish upper structure, layout, cut, weld & grind, remove downspout, prime material & clean up.
Weather - Sunny Mid 40's
Work In Progress...
Fincon - Work on canopy's, build caps and install, cut & fit, layout, weld, grind, primer, load material, clean up.
Weather - Cloudy Low 40's
Work In Progress...
Fincon - Clean out boiler room & load material, work on south canopy, layout, cut, weld, grind & prime, paint gutter inlet & trim in south mechanical room, unload material at yard.
MountainWest Security - Work on alarm system & test.
Kimco - Installed knox caps on fire riser & labeled back-flow test's.
Weather - Partly Cloudy Mid 40's
Work In progress...
Fincon - Cleaned up around north canopy's, started on south canopy, painted wall in maintenance shop, load material, finish caulking floor, cut, weld, grind & clean up.
MountainWest Security - Did a walk threw with Payson Fire Marshall & ran test's on equipment.
Weather - Partly cloudy Upper 30's
Work In Progress...
Fincon - Finish scraping caulking & sealing floor in maintenance shop, scrape snow, finish upright's on north side, clean east stairs & foundation wall, weld, paint, clean up.
Weather - Partly Cloudy Mid 40's
Work In Progress...
Fincon - Finish cleaning off tank pad, paint weir manhole, work on north canopy's, layout, cut, weld up upright's, scrub floors in maintenance room, remove rust on floors from plumber, seal floor, caulk, clean up.
G.E.C. Electric - Label panels and work on wiring in packaging room.