February 29th 2012

Work In Progress...


Fincon - Finish south canopy iron work, install decking & prime, sand & prep for paint, install last door closer, put stickers on boiler room doors, start fix on water line's in north office, load material, cut in scuffer's, clean up.
 Advanced Roofing - Start on north canopy's installing roofing. go over other fixes on east side and freezer connection.


Weather - Cloudy Low 40's










February 28th 2012

 Work In Progress...


Fincon - Finish upright's on south canopy, install fascia plate, anchor plates on wall, grind, weld, prime & clean up


Weather - Cloudy, Rain & Snow Low 30's









  

February 27th 2012

Work in progress... 


Fincon - Install fascia trim on north canopy's, sand primer, prep for paint, work on south canopy upright's, cut, weld, grind, clean up.


Weather - Partly Cloudy Upper 40's




February 24th 2012

Work In Progress...


Fincon - Work on south canopy frame, finish upper structure, layout, cut, weld & grind, remove downspout, prime material & clean up.


Weather - Sunny Mid 40's








February 23rd 2012

Work In Progress...


Fincon - Work on canopy's, build caps and install, cut & fit, layout, weld, grind, primer, load material, clean up.


Weather - Cloudy Low 40's










February 22nd 2012

Work In Progress...


Fincon - Clean out boiler room & load material, work on south canopy, layout, cut, weld, grind & prime, paint gutter inlet & trim in south mechanical room, unload material at yard.
MountainWest Security - Work on alarm system & test.
Kimco - Installed knox caps on fire riser & labeled back-flow test's.


Weather - Partly Cloudy Mid 40's






February 21st 2012

Work In progress...


Fincon - Cleaned up around north canopy's, started on south canopy, painted wall in maintenance shop, load material, finish caulking floor, cut, weld, grind & clean up.
MountainWest Security - Did a walk threw with Payson Fire Marshall & ran test's on equipment.


Weather - Partly cloudy Upper 30's















February 20th 2012

Work In Progress...


Fincon - Finish scraping caulking & sealing floor in maintenance shop, scrape snow, finish upright's on north side, clean east stairs & foundation wall, weld, paint, clean up.


Weather - Partly Cloudy Mid 40's







February 17th 2012

Work In Progress...


Fincon - Finish cleaning off tank pad, paint weir manhole, work on north canopy's, layout, cut, weld up upright's, scrub floors in maintenance room, remove rust on floors from plumber, seal floor, caulk, clean up.
G.E.C. Electric - Label panels and work on wiring in packaging room.


Weather - Partly Cloudy Low 40's