July 29th 2011

Work In Progress...




Fincon - Tie rebar, layout, install bollards, clean out bolt patterns for erectors, shoot grade, form stairs to office, clean up.
Glegg Steel - Layout for columns, set grades on bolts, get ready for standing columns.


Weather - Partly cloudy Mid 90's





July 28th 2011

Work In Progress...


Fincon - Tie rebar, pour interior footings, clean out bolt patterns, layout, start plastering interior concrete walls, clean up.
Ted Hone X - Dig interior shovel footings on south east side for office.


Weather - Sunny Mid 90's





June 27th 2011

Work In Progress...


Fincon - Pour and finish concrete, layout, chalk lines & cut concrete, 2nd pour from grid 7 - 13.
Ted Hone X - Grade and compact for concrete from grid C to F.
G.E.C. Electric - Work on underground electrical.


Weather Sunny Mid 90's







July 26th 2011

Work In Progress...


Fincon - Tie and place rebar for 2nd floor pour, set forms, shoot grades, cut out diamonds for bolt patterns, chalk lines, clean up.
Ted Hone X - Grade for concrete floor, compact, haul in base.
G.E.D. Electric - Work on underground electrical.


Weather - Sunny Mid 90s..








July 21st 2011

Work in Progress...


Fincon - layout and tie rebar for next floor pour, install pipe bollards, install exspansion between freezer and new construction, clean up.
Ted Hone X - Final grade for next concrete pour, work on subgrade, compact, haul dirt in.
G.E.C Electric - Work on underground electrical.


Weather - Sunny Mid 90's





July 20th 2011

Work In Progress...


Fincon - Pour concrete ramp, dock pit floors and floor strip south of ramp, clean floor, set forms, tie rebar, clean up.
Ted Hone X - Excavate for plumbers, grade for concrete floor, compact.
Pro Plumbing - finish sewer lines in north east bathrooms, get inspected.


Weather - Sunny Mid 90's







July 19th 2011

Work In Progress..


Fincon - Clean concrete floor, seet up dock pit, layouy, set up drains, clean up.
Ted Hone X - Excavate for plumbers, grade on floor, compact.
Pro Plumbing - Run sewer line on north end, get inspection, layout.


Weather - Partly cloudy mid 90s





July 18th 2011

Work In Progress...


Fincon - Pour 10,800 sq ft of concrete floor, finish, cut concrete, clean up.
Ted Hone X - Backfill & compact, excavate for plumber.
G.E.C. Electric - Keep an eye on underground during pour.
Pro Plumbing - Finish floor drains on south west corner, layout sewer lines.


Weather - Partly cloudy mid 90s





July 15th 2011

Work In Progress....


Fincon - Pour & finish walk ramp, Finish up tying floor rebar set 18  bollards, strip forms, place diamonds, clean up.
Ted Hone X - Excavate for plumbers, backfill & compact, work on subgrade.
Pro Plumbing -Finish drain lines on upper section.
C.E.D Electrical - Work on underground electrical.


Weather - sunny Mid 90's






July 14th 2011

Work In Progress...


Fincon - Finish forming walk ramp, tie rebar, dig holes for bollards, form up dock pit floors, layout, shoot grades, clean up.
Ted Hone X - Backfill and compact around walls, excavate for plumbers.
Pro Plumbing - Fix drains in boiler room, run drain lines to concrete boxs on north east side.
G.E.C Electric - Work on underground electrical.
R.B.G. Testing - Called and told them the cylinders for the concrete test was still sitting on site and had not yet been picked up. the cylinders were filled on july 6th. Test is no longer accurate now.


Weather - Sunny Mid 90s








July 13th 2011

Work In Progress...


Fincon - Tie and place rebar, strip forms, layout, form up walkway ramp, clean up.
Ted Hone X - Backfill around interior walls and compact, build ramp on south wall.
G.E.C Electric - Work on underground.


Weather - Partly cloudy mid 80s



July 12th 2011

Work In Progress...


Fincon - Pour west ramp to freezer, set up remaining foundation wall on grid 11 and pour, tie rebar, layout, clean up.
Ted Hone x - Grade for concrete, compact.
GEC Electric - Start on underground electrical.


Weather - Partly cloudy low 90s