July 14th 2011

Work In Progress...


Fincon - Finish forming walk ramp, tie rebar, dig holes for bollards, form up dock pit floors, layout, shoot grades, clean up.
Ted Hone X - Backfill and compact around walls, excavate for plumbers.
Pro Plumbing - Fix drains in boiler room, run drain lines to concrete boxs on north east side.
G.E.C Electric - Work on underground electrical.
R.B.G. Testing - Called and told them the cylinders for the concrete test was still sitting on site and had not yet been picked up. the cylinders were filled on july 6th. Test is no longer accurate now.


Weather - Sunny Mid 90s