Work In progress...
Fincon - Form up boiler pads on west end, pour steps & diamonds, finish concrete, work on plastering on west end, grout under columns, clean up.
Ted Hone x - Start sewer line set 1st manhole in north west corner.
Clegg steel - Work on steel erection, set joists & beams.
Weather - Sunny Mid 90's