August 2nd 2011
Work In Progress...
Fincon -
Poured remaining floor, chalk lines, cut concrete, clean up.
Ted Hone X -
Work on drain box on west end & tie in lines.
Clegg Steel -
Stand columns & unload material, layout.
Weather - Sunny low 90s