June 29th 2011

Work In Progress...


Fincon - Finish setting footings on east exterior wall, pour remaining east wall footing, strip forms, tie rebar, form up south wall footing, clean up. 
Ted Hone X - Excavate for plumbers, start backfill on tested lines, compact, haul fill in.
Pro Plumbing - Install main drain line from grid B to grid E north to south, test plembing from grid 11.5 west to grid 1 "Passed".


Weather - Rain, Wind, High 80s









June 28th 2011

Work In Progress..

Fincon - Pour north footing and 75' of east footing, strip ramp walls, strip footings, set up remaining east line, tie rebar, clean up
Pro Plumbing - Ran a air test on installed lines, No city inspector working today.

Weather - Sunny Windy  Mid 90s






June 27th 2011

Work in Progress...


Fincon - Formed and poured south ramp wall, formed north footing, tied rebar, set columns, shoot grade, layout, clean up..
Ted Hone X - Excavate for plumbers, work on south side footings, floor sub grade.
Pro Plumbing - Lay drain line, get lines ready to test, grout box's.


Weather - Sunny Mid 90s









June 24th 2011

Work In Progress...


Fincon - Pour remaining interior spot footings, set bolts, strip forms, clean up
Ted HoneX - Excavate for plumbers, screen material.
Pro Plumbing - set drain lines up to grid 9.


Weather - Low 90s 





June 23rd 2011

Work In Progress...



Fincon - Finish all spot footings on interior floor, tie rebar, epoxy, layout footings, shoot grades, first day running trucks on new road east side, passed city inspection on interior footings, clean up..
Ted Hone X - Finish interior spot footings, compact, work on outer footings, install fire riser, excavate for pro plumbing.
Pro Plumbing - work on drain lines, started 8 inch drain line heading east. 

Weather - Sunny mid 90s  "HOT"















June 22nd 2011

Work In Progress...


Fincon - Layout for fire riser & footings, form up spot footings on east side grids 10 - 12, clean up
Ted Hone X - Excavate for plumbers, screen material.
Pro Plumbing - work on drain line from grid 4 - 8.


Weather - sunny mid 80s








June 21st 2011

Work In Progress...

Fincon - Layout, Strip west foundation wall, clean forms, tie rebar, move office trailer, clean up.
Ted Hone X - Screen material, excavate for the plumbers.
Pro Plumbing - Set concrete drain box's, run drain line's from west side towards the east.

Weather - Sunny low 80s






June 20th 2011

Work In Progress...


Fincon - Poured west foundation wall, tie rebar mats for spot footings, layout, clean up.
Ted Hone X - Compact east footing line, screed material, clean up.
Pro plumbing - To wet to excavate, can not access....


Weather - sunny mid 70s







June 17th 2011

Work In Progress...

Ted Hone X - Screen material for plumbing trenches and pipe trenches also for backfill and concrete base,  passed compaction tests for spot footings on east side, only one spot footing remains. Clean up

Weather - Partly cloudy mid 70s





June 16th 2011

Work In Progress...


Fincon - Passed inspection on west wall,  Finished forming, removed concrete pad and step from east side of  freezer, clean up
Ted Hone X - Dig east side footing line, clean up


Weather - Partly cloudy Mid 70s