June 9th 2011

Work In Progress..

Fincon - Set footing's grid A -1 thru 7 and west end wall footing, layout, Tie rebar, passed city inspection on footings from grid 1 thru 9, clean up.
Ted Hone X - Subex footings on north east side, screen material, work on removing water line.
Broken Arrow X - work on road subgrade.

Weather - Sunny mid 70s