June 3rd 2011

Work in Progress..


Fincon - Layout, shoot grades, repair security fence.
Ted Hone X - Haul material from west mountain PFG pit, Finish stripping ground concrete and screen. Work on footing sub grade, dig out material . 1 load of material from westrocks mona pit to try and get compaction.
Broken Arrow X - Work on road subgrade, Dig out all the way to initial subgrade. Load trucks 4 running 3 with pups.
RB&G Engineers - Test for compaction, still no results on previous proctor numbers from samples taken.

Weather - Sunny mid 60s 