Fincon - Pour footings for west end wall, layout, clean up
Ted Hone X - Remove fire hydrant and water line from under floor. work on north east footing subgrades, get compaction tests. Also worked saturday the 11th on floor subgrade.
Broken Arrow X - Worked on south end road subgrade and fire lane.
RB&G Testing - Took density tests on north east footing subgrades.
Weather - Sunny Mid 70s



No comments:
Post a Comment