June 8th 2011

Work In Progress...


Fincon - Tie rebar, form up south side spot footings from grid 2 thru 9, place rebar, work on west end continuous footing on grid 1, put up security fence, shoot grades and layout.
Ted Hone X - Finish subgrade on footings, compact, complete from grid 1 thru 9 tested and passed. Start subgrade on grid 10 and heading east.
Broken Arrow X - Finished hauling off material, working on final subgrade in road.
RB&G Testing - Done density tests on remaining footings, passed from grid 1 thru grid 9..

Weather - Sunny High 70s