June 6th 2011

Work In Progress..


Fincon - Layout, shoot grade, help with compaction tests.
Ted Hone X - Worked on footing grades and compaction, 3 loads of bank run from westrock's mona pit,  around 150 ton, beside the 50 ton from previous friday. Still having problems with rbg and there testing.
Broken Arrow X - Worked 5 hrs on sub grade on road, 3 trucks 2 with pups.
RB&G Engineering - Took density tests on westrock material. Still have not got proctor numbers on site material. Waiting for results on four tests from previous week.

Weather - WINDY partly cloudy mid 60s