Work in progress-
-All trades pulled off of south offices until 2nd level addition is designed.
-Electrician feels buried but still runs small crew size, conflict with framers over work space-framers left for the day after finishing the riser room framing
Fincon- welded bollards, clean up, install door hardware
Hone-Prepped for asphalt, set basins for MSS
Garner- Rough-in and install ceiling lights, run MCM cable in gutter
Nutek- South office sheeting, frame fire riser room, mud & tape drywall
MSS- set wastewater basins
MWS-fire alarm install
Orion-masked off S/P room