Work In Progress...


Fincon Install framing for overhead door openers, cut asphalt,  plaster north foundation wall, remove asphalt on north end & set forms and grade for concrete, tie rebar, cut concrete & grade on west end, clean up.
Ted Hone X - Work on block retaining wall.
G.E.C. Electric - Work on electric panels on north wall, rough in center office area.
Gunthers - Install Heat duct in south office area.
Warburttons - Finish up north wall and move to south dock wall.


Weather - Sunny Mid 70's