Work In Progress...
Fincon - Pour & finish concrete, core drill for bollards, demo curbing on north buildings roof, plaster foundation on south side, clean up.
Ted Hone X - Work on retaining blocks, cut subgrade around west dock.
Gunthers - Finish duct work on south office area, install curb on roof, run line set for maintenance office.
G.E.C. Electric - Run conduit, setup panels, install electrical gutter.
Nutek - Work on plywood sheeting in packaging room, Start shetrock on west end.
Warburttons - Finish Cap on top of panels, start trimming around openings.
Weather - Sunny Mid 70's