Work In progress...
Fincon - pour remaining dock ramp, pour & finish east and west stairs to freezer, remove concrete floor for utilities on south east corner, finish window swap on north wall, core drill for bollards, sawcut & clean up.
Ted Hone X - Install block retaining wall on east side.
G.E.C Electric - Work on rough in & main power supply.
Warburttons - Install Paneling on north wall.
Garage Doors Only - Finish installing and adjusting overhead doors, 2 in boiler room and 3 dock doors.
Weather - Sunny Mid 70's