October 11th 2011

Work In Progress...


Fincon - Start hanging doors, finish up compactor framing, set forms and pour rat track and stair landing's, form up east freezer stairway, install backing in rest rooms, start cutting asphalt & clean up.
Ted Hone X - grade on roadway, install drain & line for compactor's, grade for compactor bay in dock.
Gunthers - Install duct work for freezer vents, start gas line, wire for thermostat's. 
Nutek - Hang plywood on west end.
G.E.C Electric - install gutter and work on rough in.
Advanced roofing - Work on flashing around vents.
Warburttons - Worked on east side panels, move material.
Garage Doors Only - Unloaded material, start assembly of dock doors.


Weather - Partly Cloudy With on & Off Rain   Mid 60's