Work In Progress...
Fincon - Uncover & cut concrete, Start framing of roof on pumphouse, caulk doors and trim, scrub & seal floor, haul off material, clean up.
Ted Hone X - Grade east landscape area, install landscape fabric, fill with rock, work on west side sump.
G.E.C. Electric - Run conduit, work on panels in warehouse, pull wire.
Warburttons - Finish trimming out packaging room, work on 12' tall paneling out side of packaging room.
Nutek - work on framing of upper office's.
Weather - cloudy, Windy low 40's
Work In Progress...
Fincon - Pour south paving, tie rebar haul off material, set bollards, core drill, cover concrete, saw cut concrete, clean up.
Ted Hone X - clean out sump on west side, start fabric and rock down east landscape strip.
G.E.C. Electric - Work on electrical panels and transformer in warehouse, start conduit back to main supply.
Nutek - Layout, chalk lines, start framing exterior walls.
Orion Painting - Paint handrails on freezer steps.
Warburttons - Finish up paneling in packaging room, start on the hallway.
Grin Masonry - Finish laying block walls, grout, clean up.
Weather - Sunny High 40's
Work In Progress...
Fincon - Pour tank pad, south stairway, north building drain line patch & bollards in maintenance shop, clean up west side paving, chalk lines, cut asphalt, grade for concrete, set forms, core drill for bollards, finish compactor door, clean up.
Ted Hone X - Screen material, grade for concrete.
G.E.C. Electric - Work on pulling wire in the warehouse and setting panels.
Orion Painting - Finish final coat on high walls on the west side, start handrails.
Warburttons - Install paneling in packaging area.
Grin Masonry - Work on pump house walls.
Weather - Partly cloudy Mid 40's
Work in progress...
Fincon - Jackhammer and remove concrete, excavate for drain line, install 10" pipe, backfill & compact, drill for rebar, clean up
Grin Masonry - Work on block walls of pump house, grout & install rebar.
Weather - Cloudy Low 40's
Work In Progress...
Fincon - Pour & finish west side paving, Finish windows and structural framing, form up tank pad & tie rebar, excavate trench & lay pipe in north bilding, core drill for bollards.
Ted Hone X - Excavate tank pad plumbing for mss, compact, grade & backfill for pad and south stairway.
G.E.C. Electric - Work on electrical runs to packaging & warehouse.
Glegg Steel - Install Handrails.
Grin Masonry - Start block walls on pump house.
Warburttons - Work on paneling in production room.
Mss Mechanical - Install plumbing underground beneath tank pad.
Weather - Partly Cloudy Low 50's