Fincon - Pour south paving, tie rebar haul off material, set bollards, core drill, cover concrete, saw cut concrete, clean up.
Ted Hone X - clean out sump on west side, start fabric and rock down east landscape strip.
G.E.C. Electric - Work on electrical panels and transformer in warehouse, start conduit back to main supply.
Nutek - Layout, chalk lines, start framing exterior walls.
Orion Painting - Paint handrails on freezer steps.
Warburttons - Finish up paneling in packaging room, start on the hallway.
Grin Masonry - Finish laying block walls, grout, clean up.
Weather - Sunny High 40's