Fincon - Strip foundation forms on pump house, dig out and form interior drain box, tie rebar, caulk boiler room floor, form up landscape curbing out front, work on compactor door, clean up.
Ted Hone X - Work on landscaping in front & Screed material.
Gunthers - Install controls for heating & air.
G.E.C. Electric - Hang lights in packaging room, install new transformer, wire up temporary lights in packaging room.
Warburttons - Finish paneling in maintenance room, start chemical room.
Orion painting - Paint west side doors and frames, start high walls in drying area.


Weather - Sunny Mid 40's