November 28th 2011

Work In Progress...


Fincon - Pour tank pad, south stairway, north building drain line patch & bollards in maintenance shop, clean up west side paving, chalk lines, cut asphalt, grade for concrete, set forms, core drill for bollards, finish compactor door, clean up.
Ted Hone X - Screen material, grade for concrete.
G.E.C. Electric - Work on pulling wire in the warehouse and setting panels.
Orion Painting - Finish final coat on high walls on the west side, start handrails.
Warburttons - Install paneling in packaging area.
Grin Masonry - Work on pump house walls.


Weather - Partly cloudy Mid 40's