Fincon - Form up foundation wall on pump house, clean & caulk floors, Finish installing frames for rapid door in packaging room, install door hardware, grout in drain box's, dig out material for pipe in north building, clean up.
Ted Hone X - Screen material, remove concrete out front, start digging on manhole that needs to be relocated.
Gunthers - work on heating and air in upper office.
G.E.C Electric - Install lights in warehouse, run conduit in packaging room.
Orion Paint - Finish high walls in warehouse and hallway, paint stairs & trim.
Warburttons - Finish up boiler room and start trim in drying & wash room.
Weather - Sunny Mid 40's