Fincon - Clean out saw cuts, install backing rod, caulk floor joints, install backing for overhead door openers, clean up.
Ted Hone X - Rough grade planter strip on east side, grade and set retaining blocks.
Gunthers - Started installing fans in drying area, worked on duct work under freezer.
G.E.C. Electric - Hung lights in shipping area.
Utah Door - Finished installing freezer man doors.
Garage Doors Only - Hung openers on dock doors, installed overheads on chemical room and finished maintenance shop door.
Advanced Roofing - We done a walk through and located leaks..
Orion Painting - Finished cleaning ceiling & started painting again.


Weather - Snowed till 2pm then cloudy low 40's