September 13th 2011

Work In Progress...


Fincon - Finish trim in freezer, pour 180' curb and gutter, pour in sink drain hole, work on misc iron under door frames, patch & plaster, clean forms, paint unpainted iron, clean up.
Ted Hone X - Strip dirt from south side and load trucks, Work on sewer laterals, passed inspection on the two southern laterals. Backfill & compact. 
Clegg Steel - Finish off all welding & bolting on frame and cross bracing, work on nailing and crimping decking. Passed decking inspection.
Gunthers - Finish curbs on roof, install vent pipes through decking. layout for heaters.
Advanced roofing - Set material on roof, install foam on decking.
Warburtons - Finish up siding on north building.
Pro Plumbing - Unload material layout & install roof drains.


Weather - Sunny Mid 80's