September 21st 2011

Work In Progress...


Fincon - Finish forming remaining curb & gutter, work on door and vent frames, plaster foundation, layout walls, clean up.
Ted Hone X - Move material on south end and haul off excess top soil, layout and shoot grades.
Gunthers - Work on roof top curbs, finish up dryer vents.
Pro Plumbing - Install roof drain main line.
Kimco - Test west side lines, work on east side fire sprinklers.
Advanced Roofing - Finish up everything but the edges and plumbing penetrations.
Nutek - Start framing center office area, unload material.
G.E.C. Electric - Worked on conduit in ceiling joist's and walls.


Weather - Sunny Mid 80's