Fincon - Finish forming up for gate post & opener, set up curb and gutter, work on overhead door framing, plaster walls, clean up.
Ted Hone X - Finish cutting bank on south east for block and curb & gutter, remove dirt from south end, work on sub grade up roadway.
G.E.C Electric - Install conduit in ceiling for lights
Pro Plumbing - Start roof drain lines west to east.
Advanced Roofing - Work on sealing to north building and roof drain's working east.
Weather - Partly cloudy with heavy rain at times mid 70's