September 9th 2011

Work In progress..


Fincon - Layout, shoot grades, chalk lines, cut concrete and remove, cut asphalt for lateral, grade for curb and gutter, set string lines, remove door on north wall & frame in, dig for new drain in mechanic shop for sink, paint, clean up.. 
Ted Hone X - Cut for curb and gutter, work on water lines get ready for testing, backfill & compact.
Clegg Steel - Work on decking nailing & punching, install angle on side against freezer, misc welding.
Advanced Roofing - work on sealing new roof to freezer roof, take down rain gutter & down spouts.
Warburtons - Start new white paneling on north wall west end, install all J channel on upper side so we can finish roof decking.  


Weather - Partly Cloudy low 80's