September 6th 2011





Work In Progress...


Fincon - Finish cutting off roof on existing dock area, frame up remaining fan holes, tear out door and frame, grout under framing, layout & chalk lines for interior walls, clean up
Ted Hone X  - Run water line from end of docks to south fence line and turned heading west.
Clegg Steel - Finish bridging, mechanical framing, cross braces, work on decking seams and nailing.


Weather - Partly Cloudy Mid 80's