Fincon - Pour remaining column bases & freezer floor & bollards, finish installing man door to north building, patch and plaster walls, sweep & clean up..
Ted Hone X - Work on water line, Backfill & compact , pour kickers and manhole bottom.
Clegg Steel - Passed 1st deck inspection, lay more decking, punch seams & nail off sheets, weld.
Gunthers - Finish duct work on dryers, layout.
Weather - Sunny Mid 80's