Work In Progress...


Fincon - Install tubing under doorway frames, layout gates and openers, dig footing & install rebar, grout under framework, paint unfinished iron, sweep parking lot, clean up.
Ted Hone X - Finish sewer lateral to north building, load dirt from south end, cut curb & gutter, backfill & compact.
Clegg Steel - Finish misc welding, torque bolts, nail & punch decking, load equipment. 
Gunthers - Finish setting rooftop curbing, set unit heater on west end.
Warburton's - Finish misc trim on north wall, install cap on south dock roof.
Kimco - Unload material, start layout.


Weather - Partly cloudy Mid 70's