September 22nd 2011

Work In Progress...


Fincon - Pour 130' of curb and gutter & finish, Work on overhead door framing, patch and plaster foundation walls, paint framing, clean up.
Ted Hone X - Work on sub grade west end, layout sumps on south end, screen material, haul off top soil.
Gunthers - Finish work on dryer vents, hang unit heaters.
Pro Plumbing - Plumb roof drains and main line to boiler room.
Kimco - Work on fire sprinklers south east end of building.
Nutek - Work on faming production office, start framing on west end around wash area and shop.


Weather - Sunny Mid 80's








No comments:

Post a Comment