Work In Progress...
Fincon - Dig up weir plumbing so we can reroute, plaster walls on pump house, finish blocking and framing for receiving office area, clean up.
Premier Insulation - Insulate walls & ceiling of south receiving area.
G.E.C. Electric - Work on electrical in warehouse.
Dock & Door - Adjust rapid doors in packaging room.
Orion Painting - Paint fire control room and bollards.
Weather - Cloudy low 50's
Work In Progress...
Fincon - Installed blocking in south office walls, worked on east fencing, load & unload material, locate thermostat wires buried under warburttons paneling, get 4 way inspection on offices, clean up.
G.E.C. electrical - Finish up south office wiring, pull wire to boiler room.
Weather - Cloudy Mid 40's
Work In Progress...
Fincon - Finish bollards on packaging room and south offices, finish installing fire extinguisher's, clean and sweep south dock & remove dumpster from site, work on gate fencing on east side & clean up.
G.E.C. Electric - Work on rough in on south offices, finish conduit to door controls.
Garage Doors Only - Adjust remaining overhead doors, install opener in pump house.
Weather - Cloudy Mid 30's
Work In Progress...
Fincon - Install fire Extinguisher's, clean out warehouse, stack material, install manhole cover on weir, work on bollards, help install counter tops, clean up
G.E.C. Electric - Rough in on south receiving offices, work on panels.
Gunthers - Hook up gas lines to all overhead heaters & test.
M.S.S. Mechanical - Take dimensions on vent's for pump house humidity problem.
Weather - Sunny Upper 30's
Work In Progress...
Fincon - Finish patching floor and drain in north building, scrub floors, caulk & clean up.
Weather - Sunny Upper 30's
Work In Progress...
Fincon - Strip forms from north building trench drain, load material, patch walls, seal floor in pump house, clean up.
G.E.C. Electric. - Work on heat tape that wraps the pipes on the tanks.
Weather - Sunny upper 30's
Work In Progress...
Fincon - Finish forming up trench drain walls in north building, pour & finish concrete, start mounting fire extinguisher's, clean out pump house, clean up.
G.E.C. Electric - Work on electrical in pump house, start on south office's.
M.S.S. Mechanical - Finish installing pumps & run through cycles, adjust screen, fill water heater.
Kimco - Finish heads above overhead doors, test back flow prev-enters.
Weather - Sunny Mid 30's
Work In Progress...
Fincon - Pour the bottom of the floor drains in north building & finish, layout, start forming walls of trench drains, tie rebar & clean up.
G.E.C. Electric - Wire pumps up for mss, run lines for weir controls, work on electrical in warehouse.
Advanced Roofing - Work on remaining sofit & facia on pump house, fix leaks.
M.S.S. Mechanical - Finish installation of pump's.
Weather - Snow Low 30's