Fincon - Pump out pump holes, install racking in warehouse, core drill & set bollards, clean floors, caulk, done preliminary walk threw with fire marshall, clean up.
G.E.C. Electric - Work on electrical in warehouse.
Gunthers - Finish rough in above shipping, work on controls.
M.S.S. Mechanical - Plumb tanks, mount sink, work on gas lines and flue, set tank pumps. 




Weather - Cloudy High 30's