December 29th 2011

Work In Progress...


Fincon - Installed blocking in south office walls, worked on east fencing, load & unload material, locate thermostat wires buried under warburttons paneling, get 4 way inspection on offices, clean up.
G.E.C. electrical - Finish up south office wiring, pull wire to boiler room.


Weather - Cloudy Mid 40's