December 21st 2011

Work In Progress...


Fincon - Pour the bottom of the floor drains in north building & finish, layout, start forming walls of trench drains, tie rebar & clean up.
G.E.C. Electric - Wire pumps up for mss, run lines for weir controls, work on electrical in warehouse.
Advanced Roofing - Work on remaining  sofit & facia on pump house, fix leaks.
M.S.S. Mechanical - Finish installation of pump's.


Weather - Snow Low 30's