December 7th 2011

Work In Progress...


Fincon - Finish cleaning up foundation walls in pump house, hang doors in upper office area, take down plastic and clean up in freezers.
G.E.C Electric - Work on door openers and outlets in warehouse.
Warburrtons - Install paneling on inside freezer walls on both doorways. 
Orion Painting - Paint handrails, finish primer in pump house & primer upper shipping office walls.
MountainWest Security - Mount panels in north building work on wire runs & mount fire radio antenna.




Weather - Sunny Cold  High 20's