December 2nd 2011

Work In Progress...


Fincon Install upper office window, seal floors in packaging room, work on doors and closer's, clean up.
Ted Hone X - Grade slope from asphalt south, rock in around tank pad & drain box. 
G.E.C Electric - Work on panel's in warehouse and pulling main lines into them.
Warburttons - Finish up trim and paneling. only thing left is freezer door's & shipping offices.
Orion Painting - Apply second coat of paint to bollards and handrails.
Nutek - Start Tape & Mud on the fire riser room, start hanging outer walls on new offices above shipping. 
MSS Mechanical - Start installing all above ground piping and water heater.


Weather - Partly cloudy Mid 30's