December 13th 2011

Work In Progress...


Fincon - Finish racking in chemical room, install vinyl base in mechanical room above lab office, caulk floor in pump house, finish repairing weir manhole, clean up.
Ted Hone X - Clean up south lot, grade fire road, clean up out front were manhole was removed.
G.E.C. Electric - Run electrical to rapid doors, work on electrical in pump house.
Gunthers - Run gas line main into older building and start pressure test, install thermostat's. 
Orion Painting - Paint faded panels on older freezer, clean up.
M.S.S. Mechanical - Start on heater assembly, work on piping. 
Dock & Door - Install rapid door on west side of packaging room.


Weather - Snow Mid 30's