December 22nd 2011

Work In Progress...


Fincon - Finish forming up trench drain walls in north building, pour & finish concrete, start mounting fire extinguisher's, clean out pump house, clean up. 
G.E.C. Electric - Work on electrical in pump house,  start on south office's.
M.S.S. Mechanical - Finish installing pumps & run through cycles, adjust screen, fill water heater.
Kimco - Finish heads above overhead doors, test back flow prev-enters.


Weather - Sunny Mid 30's













No comments: