Fincon - Install racking and anchor down, layout and chalk for saw cutter, tear out & sub ex for new trench drains, weld & drill angle for drains, move all material from south dock for compactor install,clean up.
G.E.C.Electric - Work on west overhead door controls & power, electrical in pump house.
Garage Doors Only - Install new door on pump house.